19 , Nov : Adani Energy Solutions Limited (AESL) on Thursday announced that it had secured a power transmission project in Bihar. The project will evacuate electricity from the upcoming 2,400 MW power plant in Pirpainti, Bhagalpur district.
AESL won the project through the Tariff Based Competitive Bidding (TBCB) mechanism. It will generate an annual tariff of Rs 500 crore once commissioned.
The company will execute the project through its Special Purpose Vehicle (SPV), Vikramshila Power Transmission Ltd. It aims to complete the work by the fourth quarter of 2028.
Kandarp Patel, CEO of Adani Energy Solutions, said the project would establish a robust power evacuation system. It would also strengthen Bihar’s transmission network and improve grid reliability.
He added that the infrastructure would enhance grid resilience and help Bihar meet its growing electricity demand. Patel reaffirmed the company’s commitment to building efficient transmission infrastructure to support India’s long-term energy security.
The project will add 881 circuit kilometres of transmission lines and 3,160 MVA of transformation capacity to AESL’s portfolio.
After completion, AESL’s transmission network will expand to 30,683 circuit kilometres. Its total transformation capacity will reach 146,585 MVA.
The project includes the construction of four Gas Insulated Substations (GIS) across Jhanjharpur, Bethauli and Begusarai. It will also involve several 400 kV and 220 kV double-circuit transmission lines.
The work includes integrating existing transmission lines and constructing additional line bays at Bakhtiyarpur.
With this project, AESL’s transmission capital expenditure portfolio has reached Rs 91,500 crore. The company is India’s largest private-sector power transmission operator.