SRINAGAR, Nov 19: Minister for PDD, Revenue, Law and Parliamentary Affairs, DMRRR and Elections, Ali Mohammad Sagar, today undertook an extensive review of the ongoing construction of the new High Court Complex at Rakh-Arth, Bemina Bypass here, and directed the concerned officers to take all necessary measures to ensure its timely completion through effective planning, close monitoring and coordinated execution.
During his visit to the project site, the Minister personally assessed the pace of construction, reviewed the physical and financial progress and took detailed feedback from the executing agencies regarding the status of various components and the requirements for completing the project within the stipulated timeframe.
The Minister was accompanied by the Chief Engineer, R&B Central, Director Litigation Kashmir, Executive Engineer concerned and Assistant Executive Engineers.
During the review, Sagar was informed that the project, which commenced in April 2022, has an approved estimated cost of ₹908.20 crore, against which an expenditure of ₹213.50 crore has been incurred so far. The main building has achieved approximately 65 per cent physical progress, with an estimated cost of around ₹450 crore, while the road component accounts for approximately ₹90 crore.
The Minister was apprised that Phase-I of the project is targeted for completion by November 2027, with the first block expected to be completed within the next six months. The tender for air-conditioning and heating systems has been allotted, while the electrical works have also been tendered.
Taking a detailed assessment of the financial requirements, Sagar was informed that approximately ₹290 crore would be required to meet the project expenditure up to November 2027. The budget provision for 2026-27 includes ₹87 crore under SASCI and ₹5.30 crore under UT Capex, while an additional requirement of ₹41 crore has been proposed under Budget Estimates 2027-28.
The Minister laid particular emphasis on reassessing the original Detailed Project Report (DPR), observing the need to factor in the time elapsed since the commencement of the project, prevailing market rates, technical requirements and the financial implications of the balance works.
He directed the concerned officers to undertake a comprehensive review of the project, including its scope, technical specifications, pending components and revised cost estimates, and prepare an updated DPR along with a realistic phase-wise execution schedule for consideration and approval of the competent authority.
Sagar stressed that proper financial planning and timely availability of funds would be crucial for maintaining the pace of construction and avoiding any delays. He called upon the executing agencies to ensure effective coordination and closely monitor every component of the project.
The Minister further emphasised that quality of construction, adherence to technical specifications and timely execution must remain the foremost priorities, adding that such a significant judicial infrastructure project requires sustained attention and accountability at every level.
It was also informed that Phase-II of the project would be taken up separately through the prescribed tendering process.
Reiterating the importance of strengthening judicial infrastructure in Jammu and Kashmir, Sagar stressed that the new High Court Complex should be developed as a modern, well-equipped and functional facility, with all essential infrastructure in place to meet the long-term requirements of the judicial institution.